| Emergency Cleanup Of Collapsed Waste
Storage Tent |
An EWP Success Story: Oak Ridge (Y–12)
On January 5, 1997, at approximately 2:30 a.m., a large canvas tent covering
a one-quarter-acre storage area for 1,500 barrels of radioactive and mixed
waste on Chestnut Ridge above the Y–12 site at Oak Ridge was blown
away by gale-force winds. An initial assessment showed that two of the
tent's four main support beams had fallen, rupturing barrels and spilling
their contents. The two remaining beams, though still standing, were only
partially connected, threatening to fall onto other barrels. The collapsed
structure created a warren of tons of steel cables, toppled beams, tent
canvas, and leaking hazardous waste containers.
Stabilizing the critical situation demanded immediate corrective action.
Detailed plans needed to be developed to ensure that the fallen beams
were cleared, the partially connected beams stabilized, waste containers
relocated, the leaking drums removed and the contents repackaged, and
the 10,000 gallons of contaminated rainwater within the facility’s
diked area cleaned up. Concomitantly, work had to proceed in accordance
with requirements and controls necessary to protect the environment and
the health and safety of those involved.
| Drum
repair kits or drum
tourniquets can be used for quick temporary repair of drums,
barrels or tanks in order to contain hazardous waste and liquids
until permanent containment can be implemented. Leaking drums can
be transfered into
overpacks or salvage drums allowing you to handle and transport
hazardous materials safely. |
As highlighted below, the incident provided an opportunity for demonstrating
many of the fundamental tenets of enhanced work planning at Oak Ridge.
Management Commitment
After Waste Management and the plant shift superintendent's office performed
initial inspections, the Maintenance General Supervisor was contacted
to lead the planning and oversee the response operations. Y–12's
rigger planner was then notified and he and the Maintenance General Supervisor
met with plant managers in the Emergency Operations Center at 4 a.m. to
determine how they would coordinate the efforts to stabilize and repair
the fallen structure safely.
The Y–12 Plant Manager and the management team emphasized that the
objective was to work safely and minimize any damage to the remaining
barrels. They made clear that the job must be planned and executed in
a safe and timely manner with a coordinated effort from all necessary
organizational groups.
Work Scope and Responsibilities Clearly Defined
Up-Front
In order of their importance, the primary necessary tasks were the clearing
of the two fallen beams and the stabilization and subsequent removal of
the standing (partially connected) beams to ensure that no additional
damage would occur. To avoid collapse of the remaining structure, the
clearing would need to be accomplished the first day. Stabilization work
would need to be coordinated with environmental personnel who were assigned
to assess, contain, and clean up releases from the barrels.
Up-Front, Multidisciplinary Planning; Worker Involvement; Parallel Review;
Job Walkdown; Hazard-Based/Graded Planning Approach
To determine how the work was to be done, a multidisciplinary planning
team was assembled at the site at dawn. The team, consisting of maintenance
supervisory personnel, a planner, ES&H support, and craftspeople,
walked the job to consider options and arrive at the best plan of attack
for each task identified. Emphasis was on drawing on the craft skills
of the workers involved. Through the collaboration of the various disciplines
involved, the planning team was able to look simultaneously at all aspects
of the job and arrive at an effective, coordinated plan.
Once the first phase of the planning was concluded, a formal lift plan
was developed and set in motion, with the participation and simultaneous
approval of the appropriate support groups (i.e., industrial safety, industrial
hygiene, environmental, engineering, quality assurance). After the two
partially connected beams were lifted into place by two large mobile cranes,
the cables and bolts still connected to them were cut so that the beams
could be properly reset. This process required close coordination between
two crane operators, two crews working out of two bucket trucks, and the
ground crew.
The same crew (already familiar with the first successfully completed
lift) then developed lift plans for each additional lift using the already-proven
planning approach. Critical-lift plans were developed and completed for
each of the four main beams. For the less critical lifts (beam disassembly,
section movement, loading), the crew did not create formal plans, instead
relying on craft skills.
| Have trained personnel in charge
to assess the site and determine what risks and hazards are present.
Preparing an effective plan is paramount for minimizing injuries,
enivironmental effects and costly damages. Dawg® offers a large
selection of safety
training materials to help keep your personnel up to date and
well trained to handle any crisis. |
Measure Performance; Draw from Lessons Learned
Operations went smoothly. Planning for the first critical lift (stabilizing
and cutting cables) took approximately 4 hours (as compared to an estimated
minimum of 2 days to plan and get all the approvals for this type of priority
critical lift per Y–12's normal procedure). Initial tasks (from
the inspection of the site, through the planning process, to eliminating
the risk posed by the two unstable beams) were safely accomplished in
13 hours. The entire cleanup effort, including removing the four main
structural beams, cutting them into smaller sections for disposal, removing
all the cabling that was holding the canvas tent in place and removing
the material from the site, was completed in 4 days.
ENHANCED WORK PLANNING APPLIED
The successful and timely cleanup of the collapsed tent incorporated many
tenets associated with Enhanced Work Planning.
- Management commitment to a safe and effective operation was displayed
by Y–12's Plant Manager and the management team from the beginning.
They clearly established the project's priority and helped remove
obstacles so that the job could run smoothly.
- Work was clearly defined up-front by a knowledgeable, committed
team who determined the scope and timing of the project along with
the resources required.
- Roles and responsibilities were clearly defined and accountabilities
were commensurate with authorities. A single person was in charge
who effectively drew on the resources at his disposal.
- Up-front, multidisciplinary planning was used that relied on craft
involvement, parallel review of plans (not sequential), and onsite
job walkdowns.
- A hazard-based, graded approach to the work was illustrated when
formal lift plans were used for high-hazard operations while craft
skills were relied on for less critical lifts.
- ES&H organizations clearly understood their support role to
operations and permits were 'driven back' to the ES&H experts
such that operations personnel (in this case the facility owners)
determined the need for the intervention of the ES&H support groups
based on their detailed knowledge of the facility and what tasks needed
to be accomplished. Operations then worked closely with the support
organizations to drive the completion of permits by the subject matter
experts and the assignment of support ES&H staff in a coordinated,
responsive manner.
- Performance was measured and compared to the status quo, and lessons
learned were communicated so that successful operations could be repeated.
In this incident at Y–12, Enhanced Work Planning helped transform
a 3-week cleanup (under Y–12's usual planning process) into a
4-day effort, without compromising worker or environmental safety. In
the words of James Stone, Deputy Division Director, Y–12 Waste
Management Division,
"During my years at the site, I can’t remember any project
that went as well. Enhanced planning maximized the effectiveness of
the 60 people involved in the project representing numerous organizations
and technical disciplines. We should capture what made this successful
and make it a standard part of doing business at Oak Ridge."
Click here to go to the EWP
- U.S. Dept of Energy, Office of environment, Safety & Health
| One of the best things we can do
is to learn from these types of events. There is plenty of documentation
of when things go wrong, but even more important is to show we have
learned from the past. As we document successful cases like this,
so that others can model to ensure other successful responses in
the future. |
|
| Be Prepared:
Are you ready for an Emergency?
Preparation and quick response are the most important factors in
handling emergency situations effectively. Having all the right
tools and equipment is a key element for successfully responding
to an emergency. Even more important, is communication and planning.
If your employees are not properly informed, educated and trained
on what to do in case of an emergency, you are destined for failure.
Proper planning, training and precautions will give your employees,
staff or community a much greater chance for success, while minimizing
risks of injury or costly effects of damage.
Dawg® offers all the products you will need to be prepared
to handle emergency situations:
Dawg® Spill Kits
& Absorbents:
We offer a large selection of emergency response kits that are filled
with absorbents to help you to respond to various types of spills.
Universal Spill Kits for absorbing a variety of
spilled liquids, chemicals and solvents.
Oil Only Spill Kits specifcally designed to absorb
oil and petroleum liquids while repeling water.
Hazmat Spill Kits for handling spills with more
aggressive chemicals.
Click
here for our helpful spill kit selection guide.
Material Handling Products:
Dawg® Material handling products help workers address proper
safety and compliance regulations When It comes to handling, moving
and storing materials.
Safety Storage Cabinets Are Ideal For Storing Flammables, Paints,
Corrosives And More.
Type I And Type II Safety Gas Cans
55 Gallon Drum Pumps Perfect For Steel And Plastic Drums Or Used
As Economical Drum Hand Pumps And Rotary Hand Pumps For Barrels.
Salvage Drums Are Ideal For Shipping Leaky Packages Or Protecting
Drums From Rupturing During Transport.
Poly And Overpack Drums Keep Drums Protected From Accidents During
Transport.
Click
here for a complete listing of Dawg® Material handling Products
Spill Containment Products:
Dawg® Spill Containment Products Provide A Safe Secondary Measure
Against Accidental Spills In Your Workplace.
Secondary Containment Pallets and Spill Decks That Can Hold Anywhere
from 1-8 Drums And Provide Adequate Secondary Spill Containment
Storage.
IBC Tanks, IBC Totes And Intermediate Bulk Containers That Hold
Large Amounts Of Liquids.
Chemical Storage Buildings Provide Safe And Compliant Hazmat Storage
Of Highly Flammable And Hazardous Materials.
Spill Containment Berms Provide Customizable Spill Storage Capacities
For All Types Of Fuel Spill Containment.
Drum Containment Accessories such as Drum Repair Kits and Tourniquets
provide quick temporary repair of leaking drums or tanks. Allowing
responders time to get proper containment in place such as overpacks
and salvage drums.
Click
here for a complete listing of Dawg® Spill Containment Products
Stormwater Pollution Prevention:
Dawg® Stormwater Management Products Help You Keep In Compliance
with Stormwater Pollution Prevention.
Stormwater Drain Protection Products Include Our Drain Guard Insert
That Catches Oil & Sediment, Curb Guard Inserts For Drains That
Are Set Into Curbing, Dewatering Bags That Contain Hydrocarbons
During Pump Out Operations For Stormwater Filtration AndScreening
Erosion Control Products Keep Stormwater Runoff From Entering Sensitive
Waterways.
Rooftop Oil Protection System That Absorbs Oil Discharge From Your
Rooftop Before Polluting Street Drains
Click
here for a complete listing of Dawg® Stormwater Protection Products
Personal Protection & Safety:
Dawg® quality protective clothing that can withstand
a variety of conditions:
Chemical protective suits, industrial coveralls, Rubber Boots &
Shoe Covers, Hearing & Respiratory Protection, Safety Gloves,
First aid Kits, Activity Drinks and Safety Glasses.
Click
here for a complete listing of Dawg® Personal Protection Products
|
|